Weekly look-ahead for week starting August 11th (night work 7:00 p.m. to 6:00 a.m. all week)
- Sunday (8/11) milling the SB lanes on the Casco Bay Bridge
- Monday (8/12) finish milling the Casco Bay Bridge & mill the side streets on Evans
- Tuesday (8/13) milling if needed to square up joints and install temp ramps
- Tues/Wed/Thurs (8/13-14-15) Crack sealing will begin once milling is complete, staring on Evans St then Ocean St then Broadway/Casco Bay Bridge